Savosolar was happy to sign its so far largest delivery contract with Grenaa Varmeværk in 2018. Savosolar’s highly efficient Savo 15 premium collectors are installed right next to an existing solar collector field which had been commissioned in 2014.
In this turn-key project Savosolar acts as the main contractor enlarging the solar fraction of the district heating network. Its operator, Grenaa Varmeværk, is producing about 146,000 MWh of heat per year. By using solar thermal it has managed to keep their customers´ heat price among the lowest in the whole of Denmark.
The new solar field with Savosolar collectors will increase the overall solar yield and ensure lowest energy production costs also in the future.
20,673 m²
Savo 15 SG-M
14.5 MW
Grenaa, Denmark
2018-2019
Solar thermal, biomass, heat pump